ResourcesCompany Update
Tungsten Mining NL (ASX: TGN) Puts $1.57 Billion Value on Watershed
Tungsten Mining’s Watershed definitive feasibility study outlines a A$1.57 billion pre-tax NPV and 70% IRR. Securing about A$255 million of remaining funding is the key next step.
![[ASX: TGN] TUNGSTEN MINING NL an elevated view of a drilling rig operating along a cleared ridge within the Watershed mineralised corridor,](/media/hero/f225b2a3-50e0-4e12-bb05-26693d654759/1794794742442-3a7f2742-1536w.webp)
Listen to article
0:00 / 3:08Tungsten Mining NL has completed a definitive feasibility study for its Watershed tungsten project in Far North Queensland, outlining a pre-tax net present value of A$1.57 billion and a 70% internal rate of return as it works towards a final investment decision in December 2026.
The base case assumes a life-of-mine ammonium paratungstate price of US$1,500 per metric tonne unit. On a post-tax basis, the project has an estimated NPV of A$1.11 billion, an IRR of 57% and a 20-month payback period from first revenue.
Total pre-production capital is estimated at A$264.4 million, including contingency. Tungsten Mining has committed A$57.8 million to early works and long-lead items, leaving go-forward pre-production capital of A$206.6 million from November 2026.
The broader peak funding requirement is estimated at A$277 million, with about A$255 million remaining. That financing requirement is now the principal hurdle between the study and full development.
Funding and offtake remain unresolved
Tungsten Mining is targeting up to 70% senior debt and has received non-binding term sheets supporting that level of project gearing. The remaining funding could include existing cash, new equity, strategic investment, equipment finance and offtake-linked facilities.
Concentrate samples have been sent to prospective counterparties in Europe, South-East Asia, the United States and Japan, with binding agreements targeted before the planned final investment decision.
The company has already started site establishment, civil works and long-lead procurement after securing the project’s principal approvals. It is targeting first production in June 2027, although that schedule depends on funding, detailed execution and the remaining activity-specific approvals.
Reserve supports 13-year processing plan
Watershed has a Probable Ore Reserve of 36.6 million tonnes grading 0.124% tungsten trioxide, containing 45,500 tonnes. The study forecasts production of 31,279 tonnes of tungsten trioxide over a 13.1-year processing life, including average steady-state output of about 2,719 tonnes a year from 2029 to 2037.
The proposed open-pit operation would process 3.5 million tonnes annually. Estimated life-of-mine C1 cash costs are US$440 per metric tonne unit, while all-in sustaining costs are US$538 per metric tonne unit. The base case produces a 62% pre-tax operating margin.
Approximately 10% of the mill feed underpinning the production target is classified as Inferred Mineral Resources and is not included in the Ore Reserve. An Ore Reserve-only evaluation at the same US$1,500 price assumption produced a pre-tax NPV of about A$1.4 billion.
Project returns remain most sensitive to tungsten prices, concentrate payability, metallurgical recovery and the Australian dollar. The study’s base price is below the US$2,675 spot assessment reported by Fastmarkets on October 23, but the company’s illustrative spot-price valuation is not its base case.
Latest TUNGSTEN MINING NL ASX Announcements
- 16 Nov 2026 · 9:05 amCompany Update
- 16 Nov 2026 · 8:18 amCompany Update
- 9 Nov 2026 · 8:21 amSecurities Administration
- 30 Oct 2026 · 3:25 pmQuarterly Reports
- 19 Oct 2026 · 5:50 pmSecurities Administration
- 19 Oct 2026 · 5:44 pmSecurities Administration
- 19 Oct 2026 · 5:37 pmSecurities Administration
- 19 Oct 2026 · 5:36 pmSecurities Administration
![[ASX: AS1] ASARA RESOURCES LIMITED a reverse-circulation drill rig operating in the weathered terrain of Guinea, framed wide to show the scale](/media/hero/6448676e-c76b-4841-ba85-d98070bbc3ea/1793920063712-12d82ee6-640w.webp)
![[ASX: MPK] MANY PEAKS MINERALS LTD a geological cutaway beneath an exploration landscape showing a broad open-pit shell above a steep, deepening](/media/hero/a4878f4c-5734-446b-b1f0-5ddddc656eed/1793847796867-85c91951-640w.webp)
![[ASX: BPM] BPM MINERALS LIMITED a reverse-circulation drill rig operating on flat, sparsely vegetated terrain in Western Australia, framed wide to show](/media/hero/7a33fc93-0df1-4250-8b4a-53992a8f2500/1793764233541-61e06540-640w.webp)
![[ASX: NVU] NANOVEU LIMITED a close-up of a semiconductor evaluation board connected to sensors and diagnostic equipment on an electronics engineer’s workbench,](/media/hero/1f39ca88-0032-4be9-b03d-40f74da80a4e/1794268166750-4dd3619d-640w.webp)
![[ASX: LDX] LUMOS DIAGNOSTICS HOLDINGS LIMITED a clinician in an urgent care examination room preparing a fingerstick blood sample beside a compact](/media/hero/14fdc9c1-090a-4cb4-838b-6ccac9e764af/1794196573830-a831dc31-640w.webp)
![[ASX: NXT] NEXTDC LIMITED a close interior view down a long data centre aisle, with symmetrical server cabinets, overhead cable trays and](/media/hero/70dce63f-62a5-454e-aec8-235390fd89e5/1793848117899-0949acda-640w.webp)