Tungsten Mining NL (ASX: TGN) Puts $1.57 Billion Value on Watershed

Tungsten Mining’s Watershed definitive feasibility study outlines a A$1.57 billion pre-tax NPV and 70% IRR. Securing about A$255 million of remaining funding is the key next step.

TGNTUNGSTEN MINING NLResources2 min read

Xinfb
[ASX: TGN] TUNGSTEN MINING NL an elevated view of a drilling rig operating along a cleared ridge within the Watershed mineralised corridor,

Listen to article

0:00 / 3:08

Tungsten Mining NL has completed a definitive feasibility study for its Watershed tungsten project in Far North Queensland, outlining a pre-tax net present value of A$1.57 billion and a 70% internal rate of return as it works towards a final investment decision in December 2026.

The base case assumes a life-of-mine ammonium paratungstate price of US$1,500 per metric tonne unit. On a post-tax basis, the project has an estimated NPV of A$1.11 billion, an IRR of 57% and a 20-month payback period from first revenue.

Total pre-production capital is estimated at A$264.4 million, including contingency. Tungsten Mining has committed A$57.8 million to early works and long-lead items, leaving go-forward pre-production capital of A$206.6 million from November 2026.

The broader peak funding requirement is estimated at A$277 million, with about A$255 million remaining. That financing requirement is now the principal hurdle between the study and full development.

Funding and offtake remain unresolved

Tungsten Mining is targeting up to 70% senior debt and has received non-binding term sheets supporting that level of project gearing. The remaining funding could include existing cash, new equity, strategic investment, equipment finance and offtake-linked facilities.

Concentrate samples have been sent to prospective counterparties in Europe, South-East Asia, the United States and Japan, with binding agreements targeted before the planned final investment decision.

The company has already started site establishment, civil works and long-lead procurement after securing the project’s principal approvals. It is targeting first production in June 2027, although that schedule depends on funding, detailed execution and the remaining activity-specific approvals.

Reserve supports 13-year processing plan

Watershed has a Probable Ore Reserve of 36.6 million tonnes grading 0.124% tungsten trioxide, containing 45,500 tonnes. The study forecasts production of 31,279 tonnes of tungsten trioxide over a 13.1-year processing life, including average steady-state output of about 2,719 tonnes a year from 2029 to 2037.

The proposed open-pit operation would process 3.5 million tonnes annually. Estimated life-of-mine C1 cash costs are US$440 per metric tonne unit, while all-in sustaining costs are US$538 per metric tonne unit. The base case produces a 62% pre-tax operating margin.

Approximately 10% of the mill feed underpinning the production target is classified as Inferred Mineral Resources and is not included in the Ore Reserve. An Ore Reserve-only evaluation at the same US$1,500 price assumption produced a pre-tax NPV of about A$1.4 billion.

Project returns remain most sensitive to tungsten prices, concentrate payability, metallurgical recovery and the Australian dollar. The study’s base price is below the US$2,675 spot assessment reported by Fastmarkets on October 23, but the company’s illustrative spot-price valuation is not its base case.